The Mill Dam Repair is Complete

Last winter's grant application process started this project, on site work began in June with the removal of the old, damaged concrete, and was completed on August 12 when the new concrete was poured. Many thanks to Joe Levesque, Board member and grant writer for Chase's Mill, Randy Rhoades of M & W Soils Engineering of Charlestown, NH, Josh Watson and his team at M & K Commercial Diving in Gilsum, NH, and Jim Gruber, former Board chair and current volunteer.

Pouring concrete on August 12. Photo credit Jim Gruber.

Next
Next

Chase’s Mill awarded Grant from the 1772 Foundation